The Government of Tamil Nadu created a Special Purpose Vehicle (SPV) named “Chennai Metro Rail Limited” (CMRL) for implementing the Chennai Metro Rail Project
Phase I of the Chennai Metro Rail project covers a length of 45.046 km network and consists of two Corridors - Corridor-1 and Corridor -2. The first segment of the section was commissioned on 29th June 2015. On 10th February 2019, the Underground stretch of the blue line was opened, completing the 45 km network.
Phase II expansion has been planned for a length of 118.9 km network with 128 nos. of Stations. It consists of three Corridor - Corridor-3, Corridor-4, and Corridor-5.
OCG is key member for the consortium rendering General Consultancy (GC) services for Chennai Metro Rail Phase 2 Project - Corridor 4 and part of Corridor-3&5
The Phase II construction work is already started and is targeted for completion by the end of 2026.
As the General Consultant, Oriental Consultants is providing the following services:
Corridors | Elevated (km) | UG(km) | Total Length (km) |
---|---|---|---|
Corridor-3 Sholinganallur to Sipcot-2 |
10.13 | 0 | 10.13 | Lighthouse to Poonamallee Bypass | 16.0 | 10.1 | 26.10 |
Corridor-5 Sholinganallur to CMBT |
24.04 | 0 | 24.04 |
Total Length | 60.27 |
Corridors | Elevated (km) | UG(km) | Total Stations |
---|---|---|---|
Corridor-3 Sholinganallur to Sipcot-2 |
9 | 0 | 9 | Corridor-4 Lighthouse to Poonamallee Bypass |
18 | 12 | 30 |
Corridor-5 Sholinganallur to CMBT |
23 | 0 | 23 |
Total Stations | 62 |
SL.NO | DESCRIPTION | NO OF PACKAGES |
---|---|---|
1 | Civil Package | 19 | 2 | Track Package | 5 |
3 | System Package | 36 |